Project management techniques used in the European Vacuum Vessel sectors procurement for ITER

M Losasso, Maria Ortiz De Zuniga, Lawrence G Jones,Angel Bayon,Jeanfrancois Arbogast,Joan Caixas, Jose Manuel Mesa Fernandez,S Galvan, Teresa Jover,K Ioki, Michal Lewczanin, Gonzalo Mico, Jose Miguel Pacheco, J Preble, Vassilis Stamos,Alexandru Trentea

Fusion Engineering and Design(2012)

引用 0|浏览3
暂无评分
摘要
The contract for the seven European Sectors of the ITER Vacuum Vessel (VV) was placed at the end of 2010 with a consortium of three Italian companies. The task of placing and the initial take-off of this large and complex contract, one of the largest placed by F4E, the European Domestic Agency for ITER, is described. A stringent quality controlled system with a bespoke Vacuum Vessel Project Lifecycle Management system to control the information flow, based on ENOVIA SmarTeam, was developed to handle the storage and approval of Documentation including links to the F4E Vacuum Vessel system and ITER International Organization System interfaces. The VV Sector design and manufacturing schedule is based on Primavera software, which is cost loaded thus allowing F4E to carry out performance measurement with respect to its payments and commitments.This schedule is then integrated into the overall Vacuum Vessel schedule, which includes ancillary activities such as instruments, preliminary design and analysis. The VV Sector Risk Management included three separate risk analyses from F4E and the bidders, utilizing two different methodologies. These efforts will lead to an efficient and effective implementation of this contract, vital to the success of the ITER machine, since the Vacuum Vessel is the biggest single work package of Europe's contribution to ITER and is the largest component of the ITER device. (C) 2011 Elsevier B.V. All rights reserved.
更多
查看译文
关键词
ITER Vacuum Vessel,Project management,Tender,Schedule,Risk,WBS, PLM
AI 理解论文
溯源树
样例
生成溯源树,研究论文发展脉络
Chat Paper
正在生成论文摘要