Innovations in Design, Construction, and Management of Pingnan Third Bridge - The Largest-Span Arch Bridge in the World

STRUCTURAL ENGINEERING INTERNATIONAL(2022)

引用 10|浏览5
暂无评分
摘要
The main bridge of Pingnan Third Bridge is a half-through concrete-filled steel tubular (CFST) arch bridge with a span of 575 m, and it is the largest-span arch bridge worldwide. Several innovative technologies were proposed and adopted with respect to the design, construction and management of Pingnan Third Bridge, including: (1) integrated design and prefabricated construction technologies based on the independent cantilever unit concept to accelerate the assembly of the steel truss for the main arch; (2) a BeiDou Navigation Satellite System (BDS) based active force control and displacement adjustment technology for the construction tower and a force optimization model for the one-time tensioning of buckled cables; (3) the vacuum-assisted filling technique integrated with an advanced timed expansion and shrinkage compensation technology that generally solved the historically stubborn defect of in-tube concrete de-bonding and voiding in the CFST arch bridge industry; (4) a novel composite bridge foundation of the diaphragm wall encapsulating a grouting-reinforced pebble layer for the northern abutment of the Pingnan Third Bridge; and (5) a new management paradigm integrating informatization and intelligent technology to promote the construction management efficiency of the large-span bridge. These proposed innovative technologies can serve as good references for the construction of similar large bridges in the future.
更多
查看译文
关键词
Pingnan Third Bridge, concrete-filled steel tubular (CFST) arch bridge, independent cantilever unit, active force control and displacement adjustment technology, timed expansion and shrinkage compensation technology, diaphragm wall encapsulating grouting-reinforced pebble layer
AI 理解论文
溯源树
样例
生成溯源树,研究论文发展脉络
Chat Paper
正在生成论文摘要