Calculation of the ground hybrid electric field of ±800kV EHV DC and 750kV UHV AC parallel transmission lines

IOP Conference Series: Earth and Environmental Science(2017)

引用 0|浏览1
暂无评分
摘要
Based on the method of time-domain upwind difference algorithm, the ground hybrid electric field is calculated. The typical tower is selected from the +/- 800kV Hami-Zhengzhou DC transmission project and the 750kV Tianshui-Baoji double-loop transmission line project. In the paper, the minimum height above ground is determined when the individual AC and DC lines meet the electric field limits, respectively. Then the article analyzes the AC and DC parallel spacing and the width of the corridor, using the weighted method to determine the control values of hybrid electric field.
更多
查看译文
关键词
hybrid electric field,transmission lines,750kv uhv ac